ISO 19650 in Saudi Arabia: EIR, BEP and CDE for project owners

ISO 19650 gives Saudi owners a shared language for asking for information and getting it back in a usable form. What each part covers, what the acronyms mean, and where owners usually go wrong.

By AIM UnitedPublished Updated 6 min read
Glass facade of the Bank AlJazira headquarters in Jeddah, an AIM United scan to BIM project
Bank AlJazira headquarters, Jeddah. Owners who set clear information requirements get models they can use for operations.

ISO 19650 in Saudi Arabia has become the default way to organise BIM on large projects, even though no Saudi law we found requires it. Giga-project packages ask for it, consultants hire for it, and government deliverables line up with it. For an owner, its value is simple: it tells you how to ask for information and how to check you got it.

What is ISO 19650?

DefinitionISO 19650 is an international series of standards for managing information over the whole life of a built asset using BIM. It sets out who asks for information, who provides it, how it is exchanged and how it is checked. It does not prescribe software.

The series has six parts:

PartCoversPublished
ISO 19650-1Concepts and principlesDecember 2018 (ISO lists it as under revision)
ISO 19650-2Delivery phase of assets: design and constructionDecember 2018
ISO 19650-3Operational phase of assetsJuly 2020
ISO 19650-4Information exchange: the criteria for each exchange2022
ISO 19650-5Security-minded approach to information managementJune 2020
ISO 19650-6Health and safety informationJanuary 2025

Most Saudi construction contracts draw on parts 1 and 2. Owners who plan to run their buildings from the model should read part 3 as well. Part 5 matters for sensitive assets such as government buildings, banks and utilities.

What are OIR, PIR, AIR and EIR?

ISO 19650 calls the owner the appointing party. The owner's requirements come in four layers, as the UK BIM Alliance, BSI and CDBB guidance sets out:

  • Organisational information requirements (OIR): what the organisation needs to know to meet its business goals. For a ministry, that might be energy use across its estate.
  • Project information requirements (PIR): what the owner needs to know about the project's purpose, design and construction.
  • Asset information requirements (AIR): what the owner needs to operate and maintain the asset, such as equipment data, warranties and maintenance intervals.
  • Exchange information requirements (EIR): what each appointed party must deliver, when and in what form. The EIR is written into each appointment.

The EIR initials once stood for employer's information requirements in older UK documents. Under ISO 19650 they mean exchange information requirements, a change the Hong Kong government's terminology guide also records. If a Saudi tender still says "employer's information requirements", it means the same document.

The most common gap we see in the Kingdom is a project with an EIR but no AIR. The model then arrives at handover with design data but without the asset data the facilities team needs. Write the AIR first and derive the EIR from it.

What is a BIM execution plan?

The BIM execution plan (BEP) is the delivery team's answer to the EIR. It explains how the team will meet each requirement: who models what, to which level of development, on which software, with which naming and classification, and on what schedule. Under ISO 19650 there is a pre-appointment BEP with the tender and a detailed BEP after appointment.

A good BEP for a Saudi project includes an element-by-element LOD table (see LOD 300 vs LOD 400 vs LOD 500), a responsibility matrix, the coordination and clash detection process, and a master information delivery plan that lists every deliverable against a date.

What is a common data environment, and what are its states?

The common data environment (CDE) is the agreed source of information for the project, where every model, drawing and document is stored, checked and shared. ISO 19650-2 expects the appointing party, or someone acting for them, to provide and manage it. The UK BIM Framework guidance also advises developing the workflows first and then choosing the software to support them.

Every information container in the CDE moves through four states:

  1. Work in progress: being developed by its author and visible only to that task team.
  2. Shared: approved for sharing with other teams or the owner, for coordination and comment.
  3. Published: authorised for use, for example for construction or asset management.
  4. Archived: a record of every transition, giving an audit trail.

The archive is the part owners forget. If the CDE sits on a contractor's platform and the contract ends, make sure the owner keeps the archive. It is your record of who issued what and when, which matters if a dispute arises.

How does ISO 19650 fit Saudi requirements?

For government-funded projects, EXPRO's National Manual for Project Management sets BIM deliverables: design data and drawings from 3D models, a BIM Manager on large BIM projects, a BIM execution plan template, LOD matrices and COBie data in IFC format. These map onto ISO 19650's EIR, BEP and AIR. An owner can use the ISO 19650 structure and include the EXPRO deliverables inside it. We cover the EXPRO requirements in is BIM mandatory in Saudi Arabia.

On giga-projects, requirements arrive with tender documents and are not public. Job adverts for BIM roles on NEOM packages, for example, ask for ISO 19650 knowledge and experience with common data environments. Our article on BIM on Saudi giga-projects sets out what is on the record.

Bank AlJazira headquarters tower in Jeddah with coordination lines, an AIM United scan to BIM project
Bank AlJazira headquarters: a laser-scan-based LOD 500 model is the starting point for asset information.

Common ISO 19650 mistakes on Saudi projects

  • Copying a requirements document from another project. An EIR written for a hospital in another country will ask for the wrong things on a school in Riyadh. Start from your own asset needs.
  • Treating the BEP as a tender formality. If nobody checks deliveries against the BEP, it stops being followed within weeks.
  • Letting each contractor run its own CDE. Several CDEs on one project break the audit trail. Use one, owned or controlled by the appointing party.
  • Skipping the information delivery plan. Without dates against each deliverable, information arrives when it suits the author, not when the project needs it.
  • Leaving security to IT. For government buildings, banks and utilities, ISO 19650-5 asks for a security-minded approach to what is shared and with whom. Decide that before the first model leaves the building.

Five steps for an owner starting with ISO 19650

  1. Write down what you need to run the asset. That is your AIR. Start with the asset types your facilities team maintains.
  2. Turn it into an EIR for each appointment. Say what information, at what LOD, in what format, at which project stage.
  3. Set up the CDE before the first appointment. Define naming, status codes and approval steps.
  4. Assess each bidder's pre-appointment BEP. Score it like any other technical submission.
  5. Check deliveries against the EIR. Accept information only when it meets the requirement, and keep the archive.

AIM United is certified to ISO 19650 and runs these steps for owners and contractors. Our BIM standards and ISO 19650 consultancy writes requirements and BEPs, and our as-built and COBie handover team delivers the asset information at the end. For operations, see digital twins and facility management.

Frequently asked questions

Is ISO 19650 mandatory in Saudi Arabia?

We found no Saudi regulation that makes ISO 19650 compulsory as of October 2026. Many government and giga-project clients structure their requirements on it, so it is the safest framework to adopt.

What does EIR stand for in ISO 19650?

Exchange information requirements. Older UK documents used the same initials for employer's information requirements. Under ISO 19650 the EIR sets out what information is needed for a particular appointment.

Who provides the common data environment?

ISO 19650-2 expects the appointing party, the owner or someone acting for them, to provide and manage the project CDE. On many Saudi projects the main contractor hosts it, which works if the owner keeps access to the archive.

Can a company be certified to ISO 19650?

Yes. Certification bodies audit organisations against the series. AIM United holds ISO 19650 certification alongside ISO 9001, 14001, 45001 and 41001.

Work with AIM United

Set up ISO 19650 on your next project

AIM United is certified to ISO 19650. We write OIR, AIR and EIR for owners, review contractors' BEPs, and set up CDE workflows that your teams will use.

Sources

  1. ISO 19650-1:2018, Part 1: Concepts and principles, ISO, December 2018 (revision under way).
  2. ISO 19650-2:2018, Part 2: Delivery phase of the assets, ISO, December 2018.
  3. ISO 19650-3:2020, Part 3: Operational phase of the assets, ISO, July 2020.
  4. ISO 19650-4:2022, Part 4: Information exchange, GCC Standardization Organization store, approved 11 August 2022.
  5. ISO 19650-5:2020, Part 5: Security-minded approach to information management, ISO, June 2020.
  6. ISO 19650-6:2025, Part 6: Health and safety information, ISO, January 2025.
  7. Information management according to BS EN ISO 19650, Guidance Part 1: Concepts, UK BIM Alliance, BSI and CDBB, April 2019.
  8. ISO 19650 Guidance Part 2: Processes for project delivery, third edition, UK BIM Framework, January 2020.
  9. BIM Harmonisation Guidelines, Appendix I: ISO 19650 terminologies (v2), Development Bureau, Hong Kong, accessed 6 October 2026.
  10. Project Automation Requirements & Deliverables Guideline (EPM-KE0-GL-000020, Rev 001), EXPRO, National Manual for Project Management, Vol. 6, 15 August 2021.
  11. BIM Manager, NEOM, Sabbar (Jacobs job posting), accessed 6 October 2026. Cited as evidence of practice on giga-project packages.

Links checked on 6 October 2026. Regulations change: confirm current requirements with the issuing authority before you rely on them.